Brownfield Project comprising:
- Closed area drain system for oily water for four paraffinic naphtha tanks in Trains 1 & 2.
- Condensate drain drum for separation of parafficinic naphtha, water and flare gas.
- Upgrading of the Electrical & Instrument systems in the bunded area of Trains 1 & 2 and Modification of F&G and DCS systems.
- Fire water network and fire fighting system.
- Concrete paving for the bunded area of existing four paraffinic naphtha tanks.
- Concrete lining for the existing earthen bund wall of Trains 1 & 2.
- Storm water drainage system for all four tanks in Trains 1 & 2.